dTechs epm Ltd. v. British Columbia Hydro and Power Authority, 2021 FC 357
Justice Fothergill - 2021-04-22
Read full decision. Automatically generated summary:
This order concerns the costs and disbursements payable to BC Hydro and Awesense by dTechs as a result of this Court’s judgment in dTechs epm Ltd v British Columbia Hydro and Power Authority, 2021 FC 190. ... For the reasons that follow, BC Hydro and Awesense are each awarded costs, including reasonable disbursements, in accordance with the high end of Column IV of Tariff B of the Federal Courts Rules. The assessment of costs will include a doubling of Tariff values, but not disbursements, after the dates of the Defendants’ respective settlement offers. Post-judgment interest will be calculated on a simple basis at a rate of 2.5% per annum.
Decision relates to:
- T-227-17 - DTECHS EPM LTD. v. BRITISH COLUMBIA HYDRO AND POWER AUTHORITY et al.